CB House605 Prospect DriveWhat-if

Timeline

Anchored on Oct 2026. Assumes an accepted offer in September 2026 and closing on October 1. Move the anchor when there is a real contract date. Columns follow the site convention: Favorable is the shortest path. The schedule does not yet model the Oct 15–Apr 15 excavation blackout; if a permit lands in that window the build, and the first usable ski season, slip by up to a further season (see the season-slip risk).

Done (Favorable)
May 2028
19 months · first ski season Dec 2028
Done (Mid)
Nov 2028
25 months · first ski season Dec 2028
Done (Unfavorable)
Oct 2029
36 months · first ski season Dec 2029

Phases

PhaseMonths (Favorable / Mid / Unfavorable)Ends (mid)Source
Offer, due diligence, closingCovenants, plat, tap status, HOA/metro-district letters.1 / 2 / 3Dec 2026Model estimate — lot contract to closing incl. covenant and survey review; replace with cited source unverified · low
Architect completes plans to permit setShorter if the Hill plans are already at DD.3 / 5 / 8May 2027Model estimate — DD→CD completion with lock-off revision; replace with cited source unverified · low
Prospect design review and Mt. CB permit2 / 3 / 5Aug 2027Model estimate — DRB + town plan check; replace with cited source unverified · low
Builder bids and contract1 / 2 / 3Jul 2027Model estimate — GC bidding in a busy valley; replace with cited source unverified · low
ConstructionSame assumption as the construction loan term. Excavation cannot start Oct 15–Apr 15 (no tapping), so a late permit slips to spring.12 / 14 / 18Oct 2028Model estimate — build duration in Mt. CB (short season); replace with cited source unverified · low
Furnishing, CO, STR license1 / 1 / 2Nov 2028Model estimate — punch list, certificate of occupancy, licensing; replace with cited source unverified · low

Mid-case schedule

Bars share one axis scaled to the unfavorable total of 36 months.