CB House605 Prospect DriveWhat-if

Risks & due diligence

Every risk carries the check that retires it. Score = likelihood × impact (1–25). 13 open, 0 in progress, 0 mitigated, 0 closed.

Top open risks

  1. No agreed family budget ceiling (20) — Agree an all-in ceiling and an equity ceiling per family.
  2. Builder pricing above the mid $/sf (16) — Get rough $/sf and schedule from two or three Gunnison Valley GCs.
  3. Prospect covenants forbid lock-off or short-term rental (15) — Order the recorded CC&Rs and PUD guide from the title company; read the STR and accessory-unit clauses.

Matrix

Cells list risk keys; colour bands: 1–3 low, 4–8 moderate, 9–14 high, 15–25 severe.

Register

RiskScoreStatusOwnerNext actionDue diligence that retires it
budget-ceiling No agreed family budget ceilingFinancing20L5 × I4OpenBoth familiesAgree an all-in ceiling and an equity ceiling per family.A number written into the scorecard.
builder-cost Builder pricing above the mid $/sfCost16L4 × I4OpenBoth familiesGet rough $/sf and schedule from two or three Gunnison Valley GCs.Two written budget estimates on the actual plan set.
covenants-str Prospect covenants forbid lock-off or short-term rentalLegal / covenants — The Town of Mt. CB has no STR cap, but its ordinance defers to private covenants.15L3 × I5OpenBoth familiesOrder the recorded CC&Rs and PUD guide from the title company; read the STR and accessory-unit clauses.Written confirmation from the HOA / metro district that a lock-off STR is permitted.
insurance Wildfire-zone insurance unavailable or far above estimateFinancing9L3 × I3OpenBoth familiesGet an indicative quote from a high-value carrier on the plan set.Bindable quote.
plans-phase Included plans are schematic only, not DD/CDCost9L3 × I3OpenBuyer's agentIdentify the architect from the title block; ask for the sheet list and phase.Architect letter stating phase, reuse rights, and completion fee.
rates Construction and permanent rates above the mid caseFinancing9L3 × I3OpenBoth familiesGet a construction-to-perm term sheet from two lenders.Term sheets with LTV, rate, and guarantee requirements.
season-slip Permit lands after Oct 15 and the build slips a seasonTimeline9L3 × I3OpenArchitectWork the design and approvals phases back from an April excavation start.Approved permit before the fall tapping cutoff.
slope-geotech Slope, soils or drainage add excavation and foundation costSite9L3 × I3OpenArchitectObtain the completed soil test noted in the listing; commission geotech if incomplete.Geotech report and a foundation concept from the engineer.
str-tax STR excise tax rises and demand softensMarket8L4 × I2OpenBoth familiesTrack the 2026 Mt. CB ballot measure; re-run the Rental page with a lower ADR.Ballot result and one season of comparable listing data.
drb-approval Design review board never approved (or rejected) the Hill plansLegal / covenants6L2 × I3OpenBuyer's agentAsk the seller and the DRB for any prior submittal record.DRB correspondence or a pre-application meeting.
taps Water and sewer taps unpaid or priced above estimateSite6L3 × I2OpenBuyer's agentAsk the listing agent for tap status; request the 2026 fee schedule from MCBWSD.District letter with tap status and fee for the floor area.
use-tax-permits Permit, plan-check and materials use tax exceed the line itemCost6L3 × I2OpenBoth familiesGet the current fee resolution and valuation policy from the Mt. CB building department.Fee estimate on the project valuation.
metro-district Metro-district mills and HOA dues double-counted or underestimatedCost3L3 × I1OpenBuyer's agentGet the parcel schedule number and the mill-levy breakdown from the assessor; confirm what dues cover.Assessor mill levy list and HOA dues statement.

Scores are the families' judgment as of the last edit of 605-prospect/risks.ts; update status there as checks complete.